Revamping Of Liquid Fuel Truck Loading Facilities
In Porto Lagos, Xanthi
OF ELINOIL S.A.
The project concerns the revamping of the existing liquid fuel truck loading facilities consisting of a new bottom loading island for four (4) products (heating diesel oil, automotive diesel oil, unleaded gasoline, marine diesel oil), vapour recovery unit capable of handling vapour from eight bottom loading arms, new pump station of four (4) pumps with 120 m3/h capacity each, new medium voltage substation of 400 KVA with EDG 160/175 KVA, truck loading automation system, as well as surrounding area works. |
Provided Services
|
Project Budget: € 1.5 million |