Substitution of Heavy Fuel Oil with N. Gas in Aluminium Plant, Ag. Nikolaos, Viotia
of ALOUMINIUM S.A.
The Project concerns the construction of natural gas pipelines and distribution network to all furnaces of Aluminium S.A. plant in Aghios Nikolaos, Viotia. It incorporates Metering station, ESD valves, isolating and safety valves, underground and above ground pipes, installation of gas trains and interconnection with Alumina, Aluminum Foundry and other auxiliary burners. Nominal capacity of the Metering Station is 25.000 m3/h at operating pressure 16/4barg. |
Provided Services
|
Project Budget: € 4 million |