Upgrading of the Existing Storage and Truck Loading Facilities
at Perama, Attica
of Shell Hellas S.A.
The project concerns the upgrading of the existing truck loading station, consisting of dismantling works of 8 out of 14 existing top loading islands, construction of 5 new bottom loading islands, expansion of trucks manoeuvring area, replacement of 11 pumps and reconstruction of fuels pumping station, modifications to interconnecting pipework, installation of loading gantries automation system and vapour recovery unit and reconstruction and extension of the electrical substation. |
Provided Services
|
Project Budget: € 3.2 million |