Brief Project Description
The Attica–Crete HVDC Interconnection (PCI) is a landmark energy project designed to secure Crete’s energy supply and enhance the stability of the Hellenic Power Transmission System (HPTS). It involves the construction of a High Voltage Direct Current (HVDC) link with a transmission capacity of 2 × 500 MW and a voltage of ±500 kV.
The interconnection includes:
- HVDC Converter Station Koumoundouros (400 kV AC / 500 kV DC) in Attica.
- HVDC Converter Station Damasta (150 kV AC / 500 kV DC) in Crete, with black start capability.
- 150 kV GIS Substation at Damasta to connect with the local grid.
Photos courtesy of: ARIADNE Interconnection | IPTO.
KEY PROJECT DATA
- Transmission capacity at 1.000 MW (2 x 500 MW).
- Two submarine 500 kV cables.
- Length: 335 km submarine HVDC cables.
- Laid in sea depths of up to 1.200 meters.
- Minimum visual & environmental nuisance.
- Zero CO₂ emissions for energy production in Crete.
SCOPE OF WORK
- Detailed Engineering Design.