PPC Amyntaio Solar PV Plant
EPC Contract Project “Oricheio Dei Amyntaio” Amyntaio Cluster 3 Amyntaio Solar Park.
Brief Project Description
The Solar PV Plant is part of nine (9) solar photovoltaic parks each under a single SPV (Solar Photovoltaic Technology), located in Northern Greece.
The Solar PV Plant is located above the mining facilities of the Greek Public Power Corporation (PPC) on excavated / backfilled ground. The solar photovoltaic installation will use either a fixed tilting suspension system or double-sided monocrystalline photovoltaic modules with a nominal power class of 585-590 Wp (+/- 5Wp).
The Project also includes the design and construction of underground MV (Medium Voltage) interconnection networks, design and construction of a new 150/33 kV HV interconnection substation and design and construction of all required interconnection works at two existing high voltage substations, one at 150/33 kV voltage levels and another at 400/33 Kv voltage levels.
Photos courtesy of: TERNA S.A.
KEY PROJECT DATA
- Power Plant Capacity: 449MWp.
- Location : 9 km SW of the town of Amyntaio,
Prefecture of Florina and Kozani, region of W. Macedonia.
SCOPE OF WORK
- Detailed Design in Electrical and I&C Engineering.